Project Description

Maryland Rt. 32 Design Build

Submitted by the Old Dominion Section

Construction Cost $33,363,000
Project Location Clarksville, Maryland
Project Owner Maryland Department of Transportation
Project Designer Whitman, Requardt and Associates, LLP
Contractor Concrete General Inc.
Completion Date September, 2019

Maryland Rt. 32

Project Description

The project consisted of the widening of 3.0 miles of MD 32 from an existing 2-lane roadway to a 4-lane divided roadway with a grass median incorporating storm water management facilities, realignment/reconstruction of interchange ramps at Linden Church Road, and connections into the existing widening at the MD 108 interchange. The project goals included completing construction as soon as possible, minimizing impacts to environmental resources, design excellence, and maintaining mobility by minimizing delays during construction, specifically any detours.

Project Features

  • Phased construction used to saved time
  • Twenty bio-swales
  • Twenty-eight grass swales
  • Five storm water management ponds
  • Four headwater pools